    If you have done good job in designing your own tables/views  or you have utilized the available table/views in Microsoft Project 2007 Professional then the next step for you is getting those tables/views printed as reports. The good thing is that you can design your own reports to show those tables in reporting layout. Having those customized report will make it easy for you to extract/distribute and publish your reports in a printed formats.

    So the idea that I will illustrate in this post is summarized as the following

    • Customize your own table with the specific fields that your boss is looking for
    • Customize your own report to show this view/table as report
    • Make this report available for all projects

    Step 1 : Customize your table

    1. Click on View => Table:  => and select More Tables

      image
    2. In the dialog below click on New

      image
    3. Enter the table information as per the image below

       image
    4. Click Ok to save your table, remember the table name “Track Summary Report”
    5. Click Apply to see your table

     

    Step 2: Create Your Own Report

    1. On the menu bar, click on Report => Reports then click on Custom

      image
    2. The dialog will list all the available reports, we will not use any of them, we will create our own, right? So click on New

      image
    3. Select Task, remember that we will design a report that will show the Tasks’ Tracking Information

      image
    4. Fill in the information for your report as per the dialog photo below

      image
    5. Click Ok after finish and click in Page Setup, usually you need to select the Landscape layout to be able to print as much information as you can in a single page. Don’t forget to set the paper size to A4

      image
    6. Click in Header and Footer tap and feel free to edit the look and feel of your report header and footer

      image
    7. Click OK, then “Preview” to preview your report

      image
    8. You are done, click Ok several time to go back to MS Project Pro 2007 main menu

    Step Three: Make this report available to all projects

    1. On the main menu Click on Tools => Organizer

      image
    2. Select Report tab, select the “Tracking Summary Report” and then click << Copy to copy it to the Global template. So it will be available for the other projects

       image
    3. Done

    Best Regards

    Bilal Okour

    MS Project 2007 Top Shortcuts

     

    Hi,

    Here are some basic shortcuts for MS Project 2007 that can speed up your daily experience with MS Project 2007

    Action Keyboard Shortcut
    Indent a task ALT + SHIFT + RIGHT ARROW
    Outdent a task ALT + SHIFT + LEFT ARROW
    Link tasks CTRL + F2
    Unlink tasks CTRL + SHIFT + F2
    Scroll to Task on Gantt Chart CTRL + SHIFT + F5
    Scroll the timescale left ALT + LEFT ARROW
    Scroll the timescale right ALT + RIGHT ARROW
    Insert Row Insert


    The complete list of the shortcuts can be found here

    http://office.microsoft.com/en-us/project/HP101550121033.aspx

    Best Regards

    Bilal Okour

    MS SharePoint Designer 2007 For Free!

     

    Microsoft announced recently that  MS SharePoint Designer 2007 is available for FREE. As per the official web site of Microsoft (http://office.microsoft.com/en-us/sharepointdesigner/FX100487631033.aspx )

    image

    For EPM 2007 customers and administrators they can change the look and feel of the projects workspaces to reflect their organization image layout.

    Best Regards

    Bilal Okour